Bastora is a village in North Goa, India. It is located on the outskirts of Mapusa town.
Local landmarks include Holy Cross School, SFS Institute, Asha Bhawan among other prominent landmarks like the renowned Tipografia Rangel.
Cajetan Church.
This parish church with Saint Cajetan as patron, was dedicated to Our Lady of Hope (Nossa Senhora de Esperanca], initially erected as a chapel in 1752. The chapel was consecrated a church on 1 May 1947.
This church, built in stone masonry, is constructed in the Neo-Roman style, which originated in Italy in the fifteenth century, with the vision of reviving the style of old Imperial Rome.
Our flat is located on the ground floor of Ganesh Apartments, the only building erected in the village as far as I can see.
At present, renovation work is on. We are waiting eagerly to move and make our home in this beautiful village of BASTORA.
I look forward to long walks and even cycle like that poder you see on top!
Some random shots of our renovation work:
Link here:
https://youtube.com/user/Aurrsa
AURIEL RIBEIRO SA is the name of the channel.
Update: I have created a Facebook group called BASTORA - BARTER, BUY, BLESS exclusively for the villagers of Bastora. If you are from this village or surrounding areas within 2 km radius, please do join. Details available on the group.
I have also created a new blog called BASTORA BLESSINGS as I will soon be moving and so this blog will become redundant. Posts archived will be available for reading but all new posts will be on the new blog. Please do save the url and follow it. Thank you for reading my posts. Leave a comment so I know how it has impacted your life.
Update 29 Sept
Kitchen window grille being fabricated |
Granite for kitchen platform being cut. |
Porch wall tiled. |
Breakfast table, moulding still not done. |
Kitchen platform. |
Porch wall tiled. |
Update: 4 October
Today the railing base, seat for steps and the garden bed was completed. Tomorrow being Dusheera I don't think the workers will come.
UPDATE: Oct 6
Today the porch floor tiles and moulding on the kitchen platform was done.
Worker moving the grille to make room for sliding windows |
Tiles we will use for our kitchen platform base. |
Tiles unopened to be returned. |
Tiles unopened to be returned. |
Today they are back again to complete their work. If all goes well, we should be moving on 29 Oct.
Railing n gate fabrication are underway. Some pictures sent earlier here for you to see how its panning out.
Painting is going to get over tomorrow. Today the second coat of paint is going up. I sent the wooden kitchen cabinet and the plant stand for painting too. Same colour as the doors.
UPDATE: 28 Oct
Butterflies 🦋🦋🦋🦋🦋🦋
Its finally here! Hours not days!!
Final touches and clean-up going on today. We couldn't start carpentry but that's ok as I would rather be present to watch what's going on.
The electrician and painters were super fast. We were so glad that we switched to another contractor for these jobs. Plumbing got over yesterday and polishing of the kitchen platform will get done today.
We also got the front area next to the porch cemented and I am going to make it pretty with some selected plants.
Here are some latest pictures of the work done.
In the hall. Plug for inverter. |
Leftover tiles used under the kitchen platform. |